Dec 26, 2020

Disconnect line requirement

The work area and surrounding areas have been cordoned off and warning signs have been placed

All personal protective equipment is available

All the energy that could affect work has been released and controlled

Close/disconnect all pumps and Lock out tag out

All valves are switched to the defined safe position and are locked out tag out

All blind plates have been installed correctly

Identify all connected lines and their Lock out Tag Out sections

Close all connected heat tracing pipes and Lock out tag out

All residual pressure has been released correctly